Finally get the go ahead to turn on my system. However, I'm out of town at the moment.
Monday, March 19, 2012
Thursday, March 15, 2012
Completion Documents Needed
Received an e-mail from Sungevity that one more document needed to be signed. I was proactive and talked to NStar on Feb 21st.
The following items are needed to complete the interconnection process.
1. photos of the array, the inverter & the external AC Disconnect
2. a copy of the Certificate of Completion
3. a copy of the signed final electrical permit (if the electrical inspector did not sign the Cert of Completion)
4. Terms & Conditions signed by Sungevity
5. Exhibit G signed by you (this will be sent upon receipt of Terms & Conditions from Sungevity)
6. Schedule Z signed by you
2. a copy of the Certificate of Completion
3. a copy of the signed final electrical permit (if the electrical inspector did not sign the Cert of Completion)
4. Terms & Conditions signed by Sungevity
5. Exhibit G signed by you (this will be sent upon receipt of Terms & Conditions from Sungevity)
6. Schedule Z signed by you
Please send these items at your earliest convenience.
Didn't get a notice from Sungevity that Exhibit G needed to be signed until Mar 15.