Completion Documents Needed


Received an e-mail from Sungevity that one more document needed to be signed. I was proactive and talked to NStar on Feb 21st. 

The following items are needed to complete the interconnection process.
1. photos of the array, the inverter & the external AC Disconnect
2. a copy of the Certificate of Completion
3. a copy of the signed final electrical permit (if the electrical inspector did not sign the Cert of Completion)
4. Terms & Conditions signed by Sungevity
5. Exhibit G signed by you (this will be sent upon receipt of Terms & Conditions from Sungevity)
6. Schedule Z signed by you
Please send these items at your earliest convenience.

Didn't get a notice from Sungevity that Exhibit G needed to be signed until Mar 15.